Improving and developing the central area in its first and second phases

02:50 PM

Project name: Improving and developing the central area in its first and second phases

Achievement rate: 50%

Elapsed Time Percentage: 92%

The scheduled end: 01/22/1444 AH

Executing contractor: Wadi Al-Khaitan Trading and Contracting Company

Site Components

- Creating pedestrian paths and adjusting some areas so that cars are not allowed to move there to humanize the central area, and use materials from nature that indicate the heritage of the city of Al-Baha, such as stones with modern materials and technologies and linking them with each other.

- Gold Market square with an area of 800 square meters

- A yard in front of the fish market with an area of 2300 square meters and includes an interactive fountain and decorative lighting.