Municipal buildings and public utilities (establishing a civil center)

03:46 PM

Project name: municipal buildings and public facilities (construction of a civil center)

Project number: 19/14/501/607/99/01/4

Contractor's name: Sadeel Al Thahabiah Contracting Company

Project cost: 8,667,464 riyals

Total project duration: 912 days

Completion rate: 59%

Elapsed time: 299%

Project Status: Ongoing

Site handover date: 6/8/1436 AH

The last action on the project: The amended schedule was approved according to letter No. (4400218913) dated 04/15/1444 AH, and the remaining procedures are being completed on the project to complete it

The scheduled date of completion: 3/3/1439 AH