Treatment of visual distortion, the second stage

01:16 PM

Project name: Treatment of visual distortion, the second phase of Al-Makhwah Governorate, Al-Baha Region

Project No.: 019/14/001/406010700/3111311

Contractor's name: Al-Haramain Trading and Contracting Company

Project cost: 1.895085 riyals

Total project duration: 150 days

Completion rate: 41%

Elapsed time: 60%

Project Status: Ongoing

The date of handing over the site: 19/1/1444 AH

The last action on the project: In progress

Scheduled end date: 6/19/1444 AH