Constructing gardens, corridors and squares - Constructing Al-Qafeel walkway

10:15 PM

Project name: constructing gardens, corridors and squares - constructing Al-Qafeel walkway

Project number: 19/14/501/406059901

Contractor Name: Saeed Murdad Al-Zahrani Contracting Est

Project cost: 1,245,832 riyals

Total project duration: 517 days

Completion rate: 65%

Elapsed time: 86%

Project Status: Ongoing

The date of handing over the site: 1/21/1443 AH

The last action on the project: The project was resumed after the suspension on 3/27/1444 AH

Scheduled end date: 6/7/1444 AH